PUBLIC INFORMATION PROGRAM
Metropolitan Water Reclamation District of Greater Chicago – PUBLIC INFORMATION PROGRAM
CONTRACT 11-404-3S – UPPER DES PLAINES INTERCEPTING SEWER 11D EXT. C REHABILITATION, NSA
Project Description
Benchmark Construction has been awarded contract 11-404-3S by the MWRD to rehabilitate 10,900 feet of 36” circular sewer, rehabilitation of twenty-six (26) manholes by spray-on products; and rehabilitation of one junction structure.
The construction is located in the Villages of Palatine, Arlington Heights and the City of Rolling Meadows, in Palatine Township, County of Cook, State of Illinois.
The Contract start date is October 3, 2023. It is anticipated that the project will be substantially completed by October 24, 2024 and will have a final completion date of December 25, 2024.
Questions / Comments
- Contact Ron Burton – Project Manager 630-497-1700 ext. 243 Email: benchmarkmwrd@bmk8.com
Progress
May 2024
Sewer cleaning and TV operations are scheduled daily in various locations between 7AM and 3PM
CIPP lining operations are scheduled for the Village of Palatine for three days of dry weather M-F which will require 24-hour continuous operation
MH rehab operations are scheduled daily in various locations between 7AM and 3PM
June 2024
Sewer cleaning and TV operations are scheduled daily in various locations between 7AM and 3PM
CIPP lining operations are scheduled for various locations for three days of dry weather M-F which will require 24-hour continuous operation
MH rehab operations are scheduled daily in various locations between 7AM and 3PM
July 2024
CIPP lining operations are scheduled for various locations for three days of dry weather M-F which will require 24-hour continuous operation
MH rehab operations are scheduled daily in various locations between 7AM and 3PM.
August 2024
CIPP lining operations are scheduled for various locations M-F during dry weather conditions which will require 24-hour continuous operation
MH rehab operations are scheduled daily in various locations between 7AM and 3PM
CIPP lining operations are scheduled for various locations M-F during dry weather conditions which will require 24-hour continuous operation
MH rehab operations are scheduled daily in various locations between 7AM and 3PM
October 2024
Work on IL RT 53 to raise buried MHs to grade
MH rehab operations are scheduled daily in various locations between 7AM and 3PM
MH rehab operations are scheduled daily in various locations between 7AM and 3PM
BENCHMARK construction
Home | Company | Municipal Infrastructure | Utilities & Contracting | Site Development | News | Contact Us
2260 Southwind Blvd.
Bartlett, IL. 60103
(630) 497.1700
© 2020 Benchmark Construction. All Rights Reserved.