PUBLIC INFORMATION PROGRAM

Metropolitan Water Reclamation District of Greater Chicago – PUBLIC INFORMATION PROGRAM

CONTRACT 11-404-3S – UPPER DES PLAINES INTERCEPTING SEWER 11D EXT. C REHABILITATION, NSA

Project Description

Benchmark Construction has been awarded contract 11-404-3S by the MWRD to rehabilitate 10,900 feet of 36” circular sewer, rehabilitation of twenty-six (26) manholes by spray-on products; and rehabilitation of one junction structure.

The construction is located in the Villages of Palatine, Arlington Heights and the City of Rolling Meadows, in Palatine Township, County of Cook, State of Illinois.

The Contract start date is October 3, 2023. It is anticipated that the project will be substantially completed by October 24, 2024 and will have a final completion date of December 25, 2024.

Questions / Comments

  • Contact Ron Burton – Project Manager 630-497-1700 ext. 243 Email: benchmarkmwrd@bmk8.com

Progress

May 2024

Sewer cleaning and TV operations are scheduled daily in various locations between 7AM and 3PM

CIPP lining operations are scheduled for the Village of Palatine for three days of dry weather M-F which will require 24-hour continuous operation

MH rehab operations are scheduled daily in various locations between 7AM and 3PM

June 2024

Sewer cleaning and TV operations are scheduled daily in various locations between 7AM and 3PM

CIPP lining operations are scheduled for various locations for three days of dry weather M-F which will require 24-hour continuous operation

MH rehab operations are scheduled daily in various locations between 7AM and 3PM

July 2024

CIPP lining operations are scheduled for various locations for three days of dry weather M-F which will require 24-hour continuous operation

MH rehab operations are scheduled daily in various locations between 7AM and 3PM.

August 2024

CIPP lining operations are scheduled for various locations M-F during dry weather conditions which will require 24-hour continuous operation

MH rehab operations are scheduled daily in various locations between 7AM and 3PM

 September 2024

CIPP lining operations are scheduled for various locations M-F during dry weather conditions which will require 24-hour continuous operation

MH rehab operations are scheduled daily in various locations between 7AM and 3PM

October 2024

Work on IL RT 53 to raise buried MHs to grade

MH rehab operations are scheduled daily in various locations between 7AM and 3PM

 November 2024

MH rehab operations are scheduled daily in various locations between 7AM and 3PM

 

BENCHMARK construction

Home  |  Company  |  Municipal Infrastructure  |  Utilities & Contracting  |  Site Development  |  News  |  Contact Us

2260 Southwind Blvd.
Bartlett, IL. 60103
(630) 497.1700

© 2020 Benchmark Construction. All Rights Reserved.